World
BBC Investigation Says Gas-Powered UK AI Data Centers Could Undermine Emissions Targets
The UK budget allows data centers to build on-site power generation facilities while waiting for grid connections. A BBC investigation found four planned hyperscale data centers are considering gas-powered generation. If run at full capacity, their annual emissions could reach 4.1 million tonnes of carbon dioxide, potentially weakening the 2050 net-zero target.
According to the BBC, UK Chancellor John Healey said in his budget speech that data centers could build on-site power generation facilities while waiting for grid connections. The BBC’s “File on 4” investigation found that four planned “hyperscale” data centers, three of them in southern England, have considered using gas-fired generation to meet their electricity demand.
Based on continuous full-capacity operation of these facilities, the BBC calculated that their electricity demand would reach 1.3 gigawatts and could produce about 4.1 million tonnes of carbon dioxide each year, more than the combined emissions of the cities of Manchester, Liverpool and Southampton. The report said this could undermine the UK’s goal of achieving net-zero emissions by 2050.
Data centers are used to run digital services such as streaming, banking and public services. New-generation artificial intelligence facilities are larger and use significantly more energy than in the past. Britain’s energy market regulator, Ofgem, said data center developers have applied for grid connections totaling 72 gigawatts, while the UK’s national peak electricity demand last year was 45 gigawatts. Some developers have been told they may have to wait as long as 10 years before grid upgrades are completed.
The UK budget proposed a “British Data Centres Covenant” requiring operators to invest in local communities, create jobs and protect water resources in exchange for priority grid connections, while allowing on-site generation when grid connections are unavailable. The government said data centers are vital to the UK economy and that the covenant also requires developers to bear a fair share of the costs they impose on the energy system. Toby Perkins, a Labour MP and chair of the House of Commons Environmental Audit Committee, said a major increase in natural gas use cannot be the way forward.