Nanxi River Grand Bridge on Wenshan-Mengzi Railway Completes China Railway's First Lattice Pier
The No. 9 lattice pier of the Nanxi River Grand Bridge on the Yunnan Wenshan-to-Mengzi railway was completed on November 12, marking the first application of a lattice pier structure in Chinese railway engineering. The pier is 105 meters tall and uses concrete-filled steel tubes and precast assembly techniques, which can save 30% to 50% of concrete and steel while improving the seismic resistance and geological adaptability of mountain bridges.
According to China Railway Kunming Bureau Group Co., Ltd., construction of the No. 9 lattice pier of the Nanxi River Grand Bridge on the Wenshan-to-Mengzi railway in Yunnan was completed on November 12. This is the first application of a "lattice pier" structure in Chinese railway engineering and marks an important technological breakthrough in the construction of high-pier bridges in mountainous areas.
The Nanxi River Grand Bridge is located in Zhicun Town, Mengzi City, Yunnan Province. It has a total length of 789.71 meters, with a maximum height difference of 118 meters between the bridge deck and the ground, making it the highest bridge along the entire Wenshan-Mengzi railway. The bridge site has dramatically undulating terrain, crosses a deeply incised valley, and has unfavorable geological conditions such as dangerous rocks, rockfalls, and developed karst.
The bridge was designed with three lattice piers in total. The No. 9 pier is 105 meters tall and is the highest bridge pier on the entire line. Its lattice portion is divided into seven segments and assembled from 176 separate components, with the largest single component weighing 24 tons. Construction was like assembling giant components at a height of 100 meters.
The builder said the concrete-filled steel-tube lattice pier is made of steel tubes and I-beams forming a trapezoidal pier body that is "wide at the bottom and narrow at the top," with high-strength concrete poured inside. It can save 30% to 50% of concrete and steel. Precast assembly can also reduce on-site pollution and construction risks while improving seismic resistance and geological adaptability.
To achieve millimeter-level assembly precision, the project team laid out a high-grade survey control network, used high-precision instruments and professional setting-out, and controlled errors through techniques such as guided positioning and dynamic fine-tuning. The Wenshan-Mengzi railway has a total length of about 116 kilometers and a design speed of 160 kilometers per hour. Once completed, it will improve the road network in southeastern Yunnan and facilitate travel along the route.