Nebius Plans $40000000000 in Spending by 2027 but Data Center Projects Are Delayed

Edition 2026-11-16 · 08:00 Beijing time

During its third-quarter earnings call, new cloud provider Nebius proposed a $40000000000 spending plan for 2027, far exceeding Wall Street expectations, with funding mainly relying on customer prepayments and loans backed by contracts. Its Microsoft data center project in New Jersey is delayed; the contract is worth up to $19400000000, only slightly more than half the capacity is planned for delivery by year-end, and the rest is delayed until the second quarter of 2027.

According to TechCrunch, new cloud company Nebius announced planned spending of $40000000000 for 2027 during its third-quarter earnings call, a scale higher than Wall Street expected. The company intends to finance data center construction through customer prepayments and loans supported by customer contracts, meaning the future value of the data centers will back current expansion.

The report argues that this model carries higher risk if projects are delayed or canceled. CEO Arkady Volozh acknowledged on the call that construction on such a large scale is not easy, delays are currently part of the industry, and Nebius cannot avoid them.

Microsoft, one of Nebius's major customers, is purchasing AI computing capacity at a data center in Vineland, New Jersey, under a contract worth as much as $19400000000, but the project is months behind schedule. Currently, only slightly more than half of Microsoft's capacity is planned for delivery by the end of the year, with the rest expected by the second quarter of 2027. Nebius Chief Product and Infrastructure Officer Andrey Korolenko said third-party operator DataOne stopped temporary power generation sooner than expected while switching to Bloom Energy fuel cells.

The report also said investigative outlet Floodlight found in August this year that at least 45 natural gas generators were operating without permits at the DataOne site. New Jersey regulators fined it $1100000, finding that it violated federal law. DataOne also faces a lawsuit from nearby residents over persistent low-frequency noise.

A summary of the Nebius contract shows that if dates are missed and replacement capacity is not provided, Microsoft can terminate the affected services after a grace period; delayed delivery also includes financial penalties. Nebius said Microsoft participated in the planning process, but did not say whether Microsoft agreed to the new dates, and Microsoft has not publicly canceled the agreement.