China’s new-type power grid investment expected to exceed 5 trillion yuan during 15th Five-Year Plan period

Edition 2026-11-18 · 08:00 Beijing time

China’s power system is simultaneously facing high shares of new energy integration and growth in new loads such as computing power and battery charging and swapping. Reports show that investment in the new-type power grid during the 15th Five-Year Plan period is expected to exceed 5000000000000 yuan, with 15 new ultra-high-voltage direct-current transmission channels put into operation, while progress will be made in digital and intelligent distribution networks, smart microgrids, new-type energy storage, AI dispatch, and virtual power plants.

China has built the world’s largest power supply system. In the first nine months of this year, total electricity consumption in society reached 8073400000000 kilowatt-hours, up 3.9% year over year. By the end of September 2026, cumulative installed wind and solar power capacity had reached 2010000000 kilowatts; fluctuations in new energy and growth in high-quality electricity demand such as battery charging and swapping and computing power are driving power-grid upgrades.

In terms of grid architecture, the Guangzhou 220-kilovolt Tianhe Tangxia flexible direct-current back-to-back project will strengthen power mutual-support capabilities among three power-supply areas. After the project is put into operation, mutual-support capacity among the areas is expected to reach 2050000 kilowatts, with up to 900000 kilowatts of power able to be supplied in support of Tianhe’s core area. Yan Xiaoqing, an expert at the State Grid Energy Research Institute, believes the new-type power grid needs coordinated planning for the main grid, distribution networks, and smart microgrids to achieve main-distribution-microgrid coordination.

Yang Zhengang, a person from the planning department of China Southern Power Grid, said investment in the new-type power grid during the 15th Five-Year Plan period is expected to exceed 5000000000000 yuan, with 15 new ultra-high-voltage direct-current transmission channels put into operation, while digital and intelligent upgrades of distribution networks and the development of smart microgrids will be promoted. Project implementation will also need to address land-resource constraints through compact layouts, underground laying, and corridor planning.

At the technology level, Ningbo’s first grid-side independent energy storage station has a scale of 50 megawatts/100 megawatt-hours and can undertake peak shaving and valley filling as well as rapid frequency response. China Southern Power Grid also uses AI models such as “Tianxiang” and “Tiyan” to forecast weather and load, releasing up to 6780000 kilowatts of new-type stored electricity during high-temperature periods.

At the service level, Shenzhen’s virtual power plant platform has connected 61 operators and more than 14000 users, with real-time adjustable load exceeding 1400000 kilowatts. When Shenzhen’s power grid load hit a record high on August 12 this year, the virtual power plant’s actual maximum response capacity reached 116000 kilowatts. The report also noted that new business forms such as computing-power and electricity coordination and direct green-power connections still face challenges involving market mechanisms, service standards, and system security.